[SOLVED]- Scheduling For an organization, the following project schedule is given. Assume that all times are in days.

Scheduling

For an organization, the following project schedule is given. Assume that all times are in days.

Task Predecessor Normal Time Crash Time Crash Cost Slope
A None 7 7 NA
B A 3 3 NA
C A 8 4 600
D A 4 4 NA
E B 6 5 600
F C, D 2 2 NA
G E, F 6 6 NA
H F 5 3 400
I G, H 4 4 NA
J I 2 2 NA

In a 3- to 4-page Microsoft Word document, address the following:

  • Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times.
  • Calculate the slack time for each activity.
  • Identify the critical path.
  • Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much.

Support your responses with examples.

Cite any sources in APA format.

Order This Solution

Ask your homework question

 

INDIVIDUAL APPROACH:
Chat with every writer who applies to your request, and view their skills and portfolio. Make the choice that’s right for you.
MANAGE YOUR ORDER:
Monitor progress and see any changes made. Have full control over every phase of the process.
COMMUNICATE:
Ask your writer questions and provide your ideas about your paper. Produce the exact result that you want.
ENJOY THE OUTCOME:
Get everything done on time with high quality. Writing papers is much simpler with us.

Ask your homework question

 

© 2017 theacademicessays. All Rights Reserved. Design & Developed by theacademicessays.
Loading...